[...]
If non-performance of a party is due to an impediment which is beyond the control of that party and could not have reasonably been foreseen by that party at the time of conclusion of the contract, such as war, civil war, strike, acts of governments, accidents, fire, explosions, natural disasters etc., and neither the impediment nor its consequences could have been avoided or overcome ("acts of God"; "force majeure", "höhere Gewalt"), that party's non-performance is excused. If non-performance is temporary, performance of the contract is suspended during that time and that party is not liable for damages to the other party. If the period of nonperformance becomes unreasonable and amounts to a fundamental non-performance, the other party may claim damages and terminate the contract.27
By December 1978, strikes, riots and other civil strife in the course of the Islamic Revolution had created classic force majeure conditions at least in Iran's major cities. By "force majeure" we mean social and economic forces beyond the power of the state to control through the exercise of due diligence. Injuries caused by the operation [of] such forces are therefore not attributable to the state for purposes of its responding for damages. Similarly, as between private parties, one party cannot claim against the other for injuries suffered as a result of delays in or cessation of performance during the time force majeure conditions prevail, unless the existence of these conditions is attributable to the fault of the Respondent party.33
The position of a state enterprise in circumstances of force majeure has been widely discussed. The starting point is acknowledged to be the principle that the separation between a state enterprise and the state itself should be respected, with the result that acts of public authority by the state may operate as force majeure and excuse the state enterprise from liability. In examining the facts in any given case to determine whether they do, the state enterprise generally must be neither privileged nor discriminated against in comparison wide the private enterprise. Certain general presumptions may be taken to apply in such cases, perhaps the strongest of which is that a state is unlikely to act in the exercise of its executive powers to the detriment of its own trading organs. Here, however, it is not disputed that the measures taken by the Government of Iran were intended as a response to a widespread problem of general application, and that [the respondent] was only one of a number of enterprises affected by them. The Tribunal therefore accepts the cement shortage as a circumstance of force majeure and one for which [the respondent] should not be held responsible.49
Under American law, as under English law since 1943, the general principle applied to equitably allocate such consequences of frustration of contract is that amounts due under the contract are to be proportioned to the extent the contract was performed. If no payment has been made, the Party which has performed is entitled to receive payment to the extent of that performace. If payment has been made, the Party which received such payment is entitled to retain that amount of money proportionate to its performance and must return any money in excess of that amount.67
If a party is unjustifiably enriched at the expense of another, that party has to pay a sum of money equal to the value of the enrichment to be determined according to the contractually agreed price or market price, including full compensation for the use (usufruct) of the subject matter of the enrichment ("Nemo sine causa alterius jactura locupletari debet"; "condictio indebiti"; "unjust enrichment").73
The Tribunal has awarded compensation based on unjust enrichment or quantum meruit in several cases, when it found that other theories of recovery were unavailable and not to award compensation would be inequitable.74 Thus, in the Tribunal's jurisprudence, unjust enrichment and quantum meruit are theories of "last resort",75 which "may not be maintained when a valid and enforceable contract exists".76 The Tribunal explained the reasons for this limitation in T.S.C.B., Inc.:
Where a valid contract exists, unjust enrichment is a derivative, or at best a secondary alternative, legal theory to an action on the contract. While there are some precedents, particularly in the United States, for permitting a claimant, if he so chooses, to sue on the basis of unjust enrichment, rather than on the contract, the preponderance of authority is to the contrary.77
The first case in which the Tribunal decided a claim for unjust enrichment was Benjamin R. Isaiah.78 In that case, the Tribunal found that the claimant was the beneficial owner of funds represented by a bank cheque drawn in January 1979 by the respondent bank's predecessor on an American bank, which cheque was subsequently dishonoured for insufficient funds. Because the payee of the cheque, a business associate of the claimant's, was an Israeli national, the Tribunal had no jurisdiction over a claim based on the cheque, as such claim would not satisfy the jurisdictional requirement of continuous ownership of the claim by a United States national from the date it arose until 19 January 1981, the date of the Algiers Declarations.79 So, the claimant asserted a claim for unjust enrichment against the Iranian bank, arguing that the bank had been given funds of which he was the beneficial owner and that it retained those funds for its own benefit and to his detriment. Citing authorities, the Tribunal noted that "[r]estitutionary theories such as unjust enrichment and enrichissement sans cause are found in the laws of many nations" and that "[i]n international law unjust enrichment is an important element of state responsibility."80 The Tribunal concluded that unjust enrichment was a "general principle[] of law."81 In awarding the claimant of the cheque, the Tribunal observed that "it would be inequitable for such a bank to be able to escape liability to the beneficial owner of the funds represented by such a dishonored check and retain the funds to which the bank has no claim."82
In Sea-Land Service, Inc., the Tribunal further explored unjust enrichment. In that case, the Tribunal found that the respondent had been unjustly enriched because, after the claimant had prematurely left Iran, the respondent used a container terminal that the claimant had constructed and operated in Iran. The Tribunal, citing authority, noted the equitable nature of the theory of unjust enrichment, which, it found, "is codified or judicially recognised in the great majority of the municipal legal systems of the world, and is widely accepted as having been assimilated into the catalogue of general principles of law available to
There must have been an enrichment of one party to the detriment of the other, and both must arise as a consequence of the same act or event. There must be no justification for the enrichment, and no contractual or other remedy available to the injured party whereby he might seek compensation from the party enriched. 86
The Tribunal has followed the rule that a subcontractor generally has no right to recover against the party that has contracted with the main contractor - i.e., against the ultimate purchaser.87 In one case, Schlegel Corp., the Tribunal has deviated from that rule and has awarded damages to a subcontractor based on unjust enrichment. The unique set of circumstances of that case, however, should be distinguished from those of the subcontractor claims rejected by the Tribunal. In Schlegel Corp., the respondent, an Iranian government agency, hired an Iranian contractor to carry out a water development project. The contractor, in turn, engaged a subcontractor - the claimant - to provide and install lining material in a reservoir. Although the claimant fully performed, the contractor failed to pay. The claimant then sought to recover against the respondent before the Tribunal based on unjust enrichment. The Tribunal found in favour of the claimant, concluding that the link between the claimant's performance and the respondent's enrichment was "sufficiently direct". In making this determination, the Tribunal highlighted three factors: first, that the respondent had itself provided for the reservoir liner specifications into the main contract with the contractor; second, that the respondent's consulting engineers had ordered the contractor to make the claimant, a "nominated subcontractor" as defined in the main contract; and, third,
With respect to quantum meruit, the Tribunal has awarded compensation on that theory where services had been performed by a contractor at the request of and with the knowledge of the other party even though they were not covered by an existing contract.92 The Tribunal noted in this connection that "[i]t is well established under . . . general principles of law that under the doctrine of quantum meruit there may be recovery for work performed."93
Concerning the computation of damages in unjust enrichment and quantum meruit cases, the Tribunal's practice has been to compensate claimants based on the extent to which the respondent state has been enriched by virtue of acquiring the property.94 In determining the compensation owed a claimant in the circumstances of a particular case, the Tribunal by and large took an approach
In one case, Sea-Land Service, Inc., Chamber One of the Tribunal formulated what it considered general rules for determining damages for unjust enrichment. It stated:
Opinions differ as to the basis of computation of damages. The predominant view seems to be that damages should he assessed to reflect the extent by which the state has been enriched. ... Important factual circumstances to be taken into account are the level of investment; the period during which the foreign investor has been able to make a profit; and the benefit actually derived by the host country from its acquisition. ... Compensation for unjust enrichment cannot encompass damages for loss of future profits. The Tribunal must aim instead to place a monetary value on the extent to which [the respondent] was enriched by its premature acquisition of the facility. ... The Tribunal must establish whether [the respondent] did in fact avail itself of the facility after [the claimant's] departure.99
The Tribunal went on to award the claimant USD 750000, which the Tribunal stated was an "approximation"; of the compensation due the claimant for the
No one may set himself in contradiction to his own previous conduct ("non concedit venire contra factum proprium"; 'l'interdiction de se contredire au detriment d'autrui').102
A right that has been forfeited may not be raised.103
In deciding questions of formation, validity, and interpretation of contracts, the Tribunal, rather than relying on the parties' assertions before it, has often relied on the parties' conduct during the course of the contract. In Pomeroy Corp., the respondent contended that the contract at issue was invalid because the official who had signed it on its behalf lacked the authority to do so. The Tribunal noted that, even if the respondent's assertions of invalidity of the contract were correct, the respondent had conducted itself in a manner that indicated that it considered the contract to be valid, by making substantial contractual payments and by
In Intrend International, Inc., the Tribunal dismissed for lack of proof a counterclaim for a contract tax allegedly due on dollar payments made pursuant to the contract but never claimed by the respondent during contract performance. In reaching that conclusion, the Tribunal noted that the behavior of the (respondent) in not deducting the tax on the U.S. dollar payments and in not demanding the amount of such tax prior to bringing this counterclaim casts doubts on its present assertion that the tax is applicable to the U.S. dollar payments.'106 In General Dynamics Corp., the Tribunal granted a claim for the reimbursement of cash advances that the claimant had paid to the respondent to cover certain expenses, although the contract did not provide for such reimbursement. Noting that, at the time of contractual performance, the respondent had not objected to the claimant's invoices for reimbursement of some of the advances, the Tribunal said that, in light of this course of conduct, the (respondent) cannot now object to making full reimbursement for the overtime advances.' The Tribunal did not say
The Tribunal has also relied on the parties' contemporaneous conduct in deciding disputes concerning performance, breach, and termination of contracts. In Rexnord Inc., the Tribunal held the respondent liable for freight charges claimed to be exorbitant because the respondent had not objected contemporaneously to those charges.108 In John Carl Warnecke and Associates, the Tribunal dismissed counterclaims for defective performance, noting that the counterclaimant had paid for the work and had not complained contemporaneously about it.109
In Collins Systems International, Inc., the Tribunal deemed it unnecessary to examine the claimant's argument, based on the language of the contracts, that the contracts had terminated in March 1980, because, "[e]ven if [the claimant's] interpretation of the contracts were accepted, the practice of the Parties both after and before November 1979 convinces the Tribunal that the contracts did not terminate prior to January 1981."110 In Westinghouse Electric Corp., the claimant, who had acquiesced in the respondent's termination of the contract in June 1977,
The Tribunal has held in several other cases that a party had waived a contractual right by failing to assert it prior to the commencement of the arbitral proceedings. In Oil Field of Texas, Inc., the Tribunal concluded that the claimant had waived whatever rights it might have had to rental payments for equipment that had been destroyed on the ground that the claimant had invoiced the lessee for the replacement cost of the equipment only.112 In Combustion Engineering, Inc., the Tribunal held that, by their conduct, the claimants had waived whatever rights they might have had to claim damages from the respondent for nonperformance.113 In Collins Systems International, Inc., the Tribunal found that the claimant had waived its claim for payment of certain invoices by failing to include them in a list of outstanding invoices that it had submitted contemporaneously to the respondent.114
The Tribunal has also considered the contemporaneous conduct of the parties in evaluating evidence of contractual performance. In this context, it has consistently held that, in the absence of contemporaneous objections or disputes, invoices or payment documents presented during the course of the contract are presumed to be correct and constitute prima facie evidence of the debt.115 For
Further, the Tribunal has regarded a party's delay in making complaints about the quality or timeliness of the other party's contractual performance as evidence undermining the credibility of those complaints117 or raising serious doubts as to the existence of (the alleged) defects'.118
The Iran United St. Claims Tribunal, by consistently applying principles of commercial law in deciding many of the commercial cases before it, has contributed significantly to the stabilization and development of a multitude of principles and rules of the lex mercatoria.119 Indeed, the development of a body of international commercial law has 'made a quantum advance due to the work of the Tribunal',120 and its jurisprudence in commercial cases represents a veritable horn of plenty for those who are called to research and apply transnational commercial law, such as international arbitral tribunals and counsel engaged in international
27CENTRAL-List Rule, reprinted in Berger, Creeping Codification, supra note 2, at p. 288, and Berger, Introduction, supra note 4, at pp. 156-157.
28For a comprehensive discussion of the Tribunal's jurisprudence in force majeure cases, see Aldrich, supra note 6, at pp. 306-320.
29Gould Marketing, Inc. v. Ministry of National Defense of lran, Interlocutory Award No. ITL 24-49-2, 3 Iran-U.S. Cl. Trib. Rep. 147, 152-53 (27 July 1983); Starrett Housing Corp. v. Islamic Republic of Iran, Interlocutory Award No. ITL 32-24-1, 4 Iran-U.S. Cl. Trib. Rep. 122, 155 (19 December 1983); Department of the Environment of the Islamic Republic of Iran v. United States of America, Award No. 107-B53-1, 5 Iran-U.S. Cl. Trib. Rep. 105, 110 (25 January 1984); Sylvania Technical Systems, Inc. v. Islamic Republic of Iran, Award No. 180-64-1, 8 Iran-U.S. Cl. Trib. Rep. 298, 308-9 (27 June 1985); International Technical Products Corp. v. Islamic Republic of Iran, Award No. 186-302-3, 9 Iran-U.S. Cl. Trib. Rep. 10, 23-24 (19 August 1985); Questech, Inc. v. Ministry of National Defense of the Islamic Republic of Iran, Award No. 191-59-1, 9 Iran-U.S. Cl. Trib. Rep. 107, 119 (25 September 1985); General Dynamics Telephone Systems Center, Inc. v. Islamic Republic of Iran, Award No. 192-285-2, 9 Iran-U.S. Cl. Trib. Rep. 153, 160 (4 October 1985); International Schools Services, Inc. v. National Iranian Copper Industries Co., Award No. 194-111-1, 9 Iran-U.S. Cl. Trib. Rep. 187, 196 (10 October 1985) ("International School Services I"); Touche Ross and Co. v. Islamic Republic of Iran, Award No. 197-480-1, 9 Iran-U.S. Cl. Trib. Rep. 284, 294-95 (30 October 1985); Phelps Dodge International Corp. v. Islamic Republic of Iran, Award No. 218-135-2, 10 Iran-U.S. Cl. Trib. Rep. 157, 173 para. 51 (19 March 1986); Computer Sciences Corp. v. Islamic Republic of Iran, Award No. 221-65-1, 10 Iran-U.S. Cl. Trib. Rep. 269, 289 (16 April 1986); Richard D. Harza v. Islamic Republic of Iran, Award No. 232-97-2, 11 Iran-U.S. Cl. Trib. Rep. 76, 91 para. 37 (2 May 1986); Ammann & Whitney v. Ministry of Housing and Urban Development, Award No. 248-198-1, 12 Iran-U.S. Cl. Trib. Rep. 94, 104 (25 August 1986); American Bell International Inc. v. Islamic Republic of Iran, Award No. 255-48-3, 12 Iran-U.S. Cl. Trib. Rep. 170, 184 para. 47 (19 September 1986); Henry, F. Teichmann, Inc. v. Hamadan Glass Co., Award No. 264-264-1, 13 Iran-U.S. Cl. Trib. Rep. 124, 133 paras. 31-32 (12 November 1986); Anaconda Iran, Inc. v. Islamic Republic of Iran, Interlocutory Award No. ITL 65-167-3, 13 Iran-U.S. Cl. Trib. Rep. 199, 212-13 paras. 47-50 (10 December 1986); Ford Aerospace & Communications Corp. v. Islamic Republic of Iran, Award No. 289-93-1, 14 Iran-U.S. Cl. Trib. Rep. 24, 35-36 paras. 45-46 (29 January 1987); International Schools Services, Inc. v. Islamic Republic of Iran, Award No. 290-123-1, 14 Iran-U.S. Cl. Trib. Rep. 65, 73 para. 27 (29 January 1987) ("International School Services II"); Exxon Research and Engineering Co. v. National Iranian Oil Co., Award No. 308-155-3, 15 Iran-U.S. Cl. Trib. Rep. 3, 11 para. 30 (9 June 1987); Reliance Group, Inc. v. Oil Service Company of Iran, Award No. 315-115-3, 16 Iran-U.S. Cl. Trib. Rep. 257, 269-71, paras. 46, 51 (10 September 1987); Mobil Oil Iran Inc. v. Islamic Republic of Iran, Award No. 311-74/76/81/150-3, 16 Iran-U.S. Cl. Trib. Rep. 3, 38-39 paras. 114-17 (14 July 1987); Harris International Telecommunications, Inc. v. Islamic Republic of Iran, Award No. 323-409-1, 17 Iran-U.S. Cl. Trib. Rep. 31, 67 paras. 121-22 (2 November 1987); Lockheed Corp. v. Islamic Republic of Iran, Award No. 367-829-2, 18 Iran-U.S. Cl. Trib. Rep. 292, 302 para. 40 (9 June 1988); Motorola, Inc. v. Iran National Airlines Corp., Award No. 373-481-3, 19 Iran-U.S. Cl. Trib. Rep. 73, 80 para. 36, 85 para. 56 (28 June 1988); Avco Corp. v. Iran Aircraft Industries, Award No. 377-261-3, 19 Iran-U.S. Cl. Trib. Rep. 200, 216-17 paras. 79-80 (18 July 1988); Houston Contracting Co. v. National Iranian Oil Co., Award No. 378-173-3, 20 Iran-U.S. Cl. Trib. Rep. 3, 28 para. 87, 48-49 paras. 155-57 (22 July 1988); Stephen G. Shifflette v. Islamic Republic of Iran, Award No. 423-10645-1, 22 Iran-U.S. Cl. Trib. Rep. 111, 115-16 para. 19 (12 June 1989); Watkins-Johnson Co. v. Islamic Republic of Iran, Award No. 429-370-1, 22 Iran-U.S. Cl. Trib. Rep. 218, 242 para. 89 (28 July 1989); Electronic Systems International, Inc. v. Ministry of Defense of the Islamic Republic of Iran, Award No. 430-814-1, 22 Iran-U.S. Cl. Trib. Rep. 339, 355 para. 61 (28 July 1989); Rockwell International Systems, Inc. v. Islamic Republic of Iran, Award No. 438-430-1, 23 Iran-U.S. Cl. Trib. Rep. 150, 170 para. 88 (5 September 1989); Combustion Engineering, Inc. v. Islamic Republic of Iran, Award No. 506-308-2, 26 Iran-U.S. Cl. Trib. Rep. 60, 77 para. 61, 80 para. 71 (18 February 1991); General Electric Co. v. Islamic Republic of Iran, Award No. 507-386-1, 26 Iran-U.S. Cl. Trib. Rep. 148, 180 para. 111 (15 March 1991); Petrolane, Inc. v. Islamic Republic of Iran, Award No. 518-131-2, 27 Iran-U.S. Cl. Trib. Rep. 64, 80-81 paras. 48-51 (14 August 1991); William J. Levitt v. Islamic Republic of Iran, Award No. 520-210-3, 27 Iran-U.S. Cl. Trib. Rep. 145, 166-67 para. 71 (29 August 1991); Collins Systems International, Inc. v. Navy of the Islamic Republic of Iran, Award No. 526- 431-2, 28 Iran U.S. Cl. Trib. Rep. 21, 35 para. 43 (20 January 1992); W. Jack Buckameier v. Islamic Republic of Iran, Award No. 528-941-3, 28 Iran-U.S. Cl. Trib. Rep. 53, 84-85 para. 95 (6 March 1992); Unidyne Corp. v. Islamic Republic of Iran, Award No. 551-368-3, 29 Iran-U.S. Cl. Trib. Rep. 310, 340-42 paras. 94-97 (10 November 1993); Westinghouse Electric Corp. v. Islamic Republic of Iran Air Force, Award No. 579-389-2, 33 Iran-U.S. Cl. Trib. Rep. 60, 78 para. 54, 80 paras. 60-61 (26 March 1997); Bank Markazi Iran v. The Federal Reserve Bank of New York, Award No. 595-823-3, para. 75 (16 November 1999) (not yet published in the Iran-U.S. Claims Tribunal Reports).
30See, e.g., Anaconda Iran, Inc., supra note 29, 13 Iran-U.S. Cl. Trib. Rep. 211 para. 43 ("Under a variety of names most, if not all, legal systems recognize force majeure as an excuse for contractual non-performance. Force majeure therefore can be considered a general principle of law"); Mobil Oil Iran Inc., supra note 29, 16 Iran-U.S. Cl. Trib. Rep. 39 para. 117.
31Anaconda Iran Inc., supra note 29, 13 Iran-U.S. Cl. Trib. Rep. 211 para. 43. See also Mobil Oil Iran Inc., supra note 29, 16 Iran-U.S. Cl. Trib. Rep. 39 para. 117 (force majeure is a general principle of law that applies "even when the contract is silent").
32Gould Marketing, Inc. (Interlocutory Award), supra note 29, 3 Iran-U.S. Cl. Trib. Rep. 147.
33Id. at pp. 152-53.
34Sylvania Technical Systems, Inc. supra, note 29, 8 Iran-U.S. Cl. Trib. Rep. 298.
35Id. at p. 309.
36Id. at p. 312.
37See text accompanying note 33.
38Sylvania Technical Systems, Inc., supra note 29, 8 Iran-U.S. Cl. Trib. Rep. 309-10.
39Id. at p. 312. In rejecting the respondent's plea of force majeure, the Tribunal noted that the Iranian government had terminated the contract at issue as a result of a "deliberate policy decision not to continue with American contractors in a project that related to secret military intelligence operations" and that such a decision had been taken in view of an historic development, and do[es] not convey that performance by the [respondent] was prevented by events beyond its control. Id. at pp. 312-13.
40International Technical Products Corp., supra note 29, 9 Iran-U.S. Cl. Trib. Rep. 24.
41See ibid.
42Starrett Housing Corp., supra note 29, 4 Iran-U.S. Cl. Trib. Rep. 155.
43International Technical Products Corp., supra note 29, 9 Iran-U.S. Cl. Trib. Rep. 24.
44On 14 November 1979, US President Carter imposed economic sanctions on Iran in response to the 4 November seizure of the United States Embassy in Tehran. See text accompanying note 8.
45See, e.g., Gould Marketing, Inc. v. Ministry of National Defense of Iran, Final Award No. 136-49/50-2, 6 Iran-U.S. Cl. Trib. Rep. 272, 279 (29 June 1984); Avco Corp., supra note 29, 19 Iran-U.S. Cl. Trib. 216-17 paras. 79-80; Collins Systems International, Inc., supra note 29, 28 Iran-U.S. Cl. Trib. Rep. 35 para. 43; Unidyne Corp., supra note 29, 29 Iran-U.S. Cl. Trib. Rep. 342 para. 97.
46See e.g., Gould Marketing, Inc. (Final Award), supra note 45, 6 Iran-U.S. Cl. Trib. Rep. 279; Westinghouse Electric Corp., supra note 29, 33 Iran-U.S. Cl. Trib. Rep. 171-72 paras. 367-68.
47Blount Brothers Corp. v. Islamic Republic of Iran, Award No. 215-52-1, 10 Iran-U.S. Cl. Trib. Rep. 56 (6 March 1986).
48The question of the invocation of force majeure by a government agency for actions by its own government has been the subject of much debate. See, e.g., Karl-Heinz Böckstiegel, Arbitration and State Enterprises (Kluwer Law and Taxation Publisher, Deventer/Antwerp/Boston/Frankfurt/London, 1984) at pp. 37-39; Georges R. Delaume Law and Practice of Transnational Contracts (Oceans Publications Inc., New York/London/Rome 1988) at pp. 54-57; Thomas E. Carbonneau, "The Elaboration of Substantive Legal Norms and Arbitral Adjudication: The Case of the Iran-United States Claims Tribunal" in The Iran-United States Claims Tribunal 1981-1983 - Seventh Sokol Colloquium (ed. Richard B. Lillich) (University Press of Virginia Charlottesville, 1984) at pp. 104, 116-17, 120.
49Blount Brothers Corp., supra note 47, 10 Iran-U.S. Cl. Trib. Rep. 75. See also Bank Markazi Iran, supra note 29, at paras. 75-76 (holding, even if the Federal Reserve Bank of New York were considered an entity controlled by the government of the United States, it could, in the circumstances, invoke force majeure since it has its own legal personality distinct from the state). Accord C. Czarnikow Ltd. v. Centrala Handlu Zagranieznego Rolimpex, 1979 A.C. 351, discussed in Delaume, supra note 48, at p. 55, and Carbonneau, supra note 48, at pp. 116-17.
50See, e.g., Gould Marketing. Inc. (Interlocutory Award), supra note 29, 3 Iran-U.S. Cl. Trib. Rep. 153; Sylvania Technical Systems, Inc., supra note 29, 8 Iran-U.S. Cl. Trip. Rep. 309-10; Anaconda Iran, Inc., supra note 29, 13 Iran-U.S. Cl. Trib. Rep. 211 para. 41; General Electric Co., supra note 29, 26 Iran-U.S. Cl. Trib. Rep. 180 para. 111; Westinghouse Electric Corp., supra note 29, 33 Iran-U.S. Cl. Trib. Rep. 78 para. 54.
51The CENTRAL-List force majeure Rule provides that the affected party's "non-performance is excused" and that, "[i]f non-performance is temporary, performance of the contract is suspended during that time". See text accompanying note 27.
52See supra notes 29 and 32.
53Gould Marketing, Inc. (Interlocutory Award), supra note 29, 3 Iran-U.S. Cl. Trib. Rep. 154.
54See, e.g., International Schools Services I, supra note 29, 9 Iran-U.S. Cl. Trib. Rep. 196; Anaconda Iran, Inc., supra note 29, 13 Iran-U.S. Cl. Trib. Rep. 211 para. 41; International Schools Services II, supra note 29, 14 Iran-U.S. Cl. Trib. Rep. 72-73 paras. 23, 27; Mobil Oil Iran Inc., supra note 29, 16 Iran-U.S. Cl. Trib. Rep. 39 para. 117; Stephen G. Shifflette, supra note 29, 22 Iran-U.S. Cl. Trib. Rep. 15-16 para. 19; Combustion Engineering, Inc., supra note 29, 26 Iran-U.S. Cl. Trib. Rep. 77 para 61, 80 para. 71, 116 para. 207; William, J. Levitt, supra note 29, 27 Iran-U.S. Cl Trib. Rep. 166-67 para. 71; Unidyne Corp., supra note 29, 29 Iran-U.S. Cl. Trib. Rep. 342 paras. 97-98; Westinghouse Electric Corp., supra note 29, 33 Iran-U.S. Cl. Trib. Rep. 80 para. 61, 136 para. 259, 169 para. 360, 175 para. 379. See also Queens Office Tower Associates v. Iran National Airlines Corp., Award No. 37-172-1, 2 Iran-U.S. Cl. Trib. Rep 247, 251-52 (15 April 1983) (finding that an Iran Air lease of certain office commercial space in New York had been subject to a "combination of frustration of purpose and impossibility of payment" due to United States economic sanctions against Iran); Linen, Fortinberry and Associates, Inc. v. Islamic Republic of Iran, Award No. 372-10513-2, 19 Iran-U.S. Cl. Trib. Rep. 62, 70 para. 28 (28 June 1988) (holding that the purpose of a contract pursuant to which an American public relations firm was to promote the public image in the United States of the Pahlavi dynasty's Iran was frustrated by the success of the Islamic Revolution).
55The CENTRAL-List force majeure Rule, however, does deal with the situation where continued suspension of contractual performance becomes attributable to one of the parties: "If the period of non-performance becomes unreasonable and amounts to a fundamental non-performance, the other party may claim damages and terminate the contract." See text accompanying note 27.
56See supra note 54.
57See John A. Westberg, International Transactions and Claims Involving Government Parties - Case Law of the Iran-United States Claims Tribunal (International Law Institute, Washington D.C., 1991) at pp. 168-71, 182; Crook, "Debt and Contract Claims", supra note 22, at pp. 288-290; Crook, "Applicable Law", supra note 22, at p. 294.
58Sylvania Technical Systems, Inc., supra note 29, 8 Iran-U.S. Cl. Trib. Rep. 309, and text accompanying note 35 ("Sylvania-test").
59Westberg, supra note 57, at p. 182.
60See Sylvania Technical Systems, Inc., supra note 29, 8 Iran-U.S. CL. Trib. Rep. 308-10, 312-13, and supra note 39.
61Gould Marketing, Inc. (Interlocutory Award), supra note 29, 3 Iran-U.S. Cl. Trib. Rep. 153.
62Ibid.
63Ibid.
64See ibid. at p. 154.
65Sylvania-test, see supra note 58.
66Queens Office Tower Associates, supra note 54, 2 Iran-U.S. Cl. Trib. Rep. 254.
67Gould Marketing, Inc. (Final Award), supra note 45, 6 Iran-U.S. Cl. Trib. Rep. 274 (footnote omitted).
68See International School Services I, supra note 29, 9 Iran-U.S. Cl. Trib. Rep. 196-97; Phelps Dodge International Corp., supra note 29, 10 Iran-U.S. Cl. Trib. Rep. 173 para. 52; International Schools Services II, supra note 29, 14 Iran-U.S. Cl. Trib. Rep. 73-74 para. 30; William J. Levitt, supra note 29, 27 Iran-U.S. Cl. Trib. Rep. 167-68 paras. 74-76; Unidyne Corp., supra note 29, 29 Iran-U.S. Cl. Trib. Rep. 342-43 para. 99; Westinghouse Electric Corp., supra note 29, 33 Iran-U.S. Cl. Trib. Rep. 80-81 paras. 63-64. In Westinghouse Electric Corp., ibid. at p. 81 para. 64, the Tribunal set forth in clear and simple terms how it would determine who owed what to whom as a result of the frustration of the contracts at issue: "[The Tribunal] will determine the extent to which [the claimant] performed its obligations under each ... contract ... until such performance was made impossible, and whether, based on such performance, [the claimant] is entitled to receive further payments or, on the contrary, must return to the [respondent] part of the payments it received." See also Lockheed Corp., supra note 29, 18 Iran-U.S. Cl. Trib. Rep. 303 para. 40 (holding that whether a contract is considered ultimately frustrated or expired by its own terms makes no difference in the settlement of accounts between the parties and the determination of what one owes to whom).
69See, e.g., International School Services I, supra note 29, 9 Iran-U.S. Cl. Trib. Rep. 197-99 (awarding costs incurred prior to the date of termination of a contract to operate a school for American children in Iran, but rejecting claims for costs incurred after such date, including transportation and moving expenses, and for lost profits); Stephen G. Shifflette, supra note 29, 22 Iran-U.S. Cl. Trib. Rep. 115-16 para. 19 (awarding compensation for the two weeks the claimant worked pursuant to a contract for teaching services in Iran, but not lost wages for the remainder of the semester); Combustion Engineering, Inc., supra note 29, 26 U.S. Cl. Trib. Rep. 77 paras. 62, 207 (dismissing claims for licence fees due subsequent to the termination of the licensing agreement); Unidyne Corp., supra note 29, 29 Iran-U.S. Cl. Trib. Rep. 344 paras. 102-103 (awarding compensation for work performed but not paid for, but denying a claim for lost profits); Westinghouse Electric Corp., supra note 29, 33 Iran-U.S. Cl. Trib. Rep. 81 para. 64, 126 para. 216 (awarding compensation for work performed but not paid for, but denying claim for lost profits).
70Westinghouse Electric Corp., supra note 29.
71Id. 33 Iran-U.S. Cl. Trib. Rep. 80 para. 62; International Schools Services I, supra note 29, 9 Iran-U.S. Cl. Trib. Rep. 196-97.
72See, e.g. Unidyne Corp., supra note 29, 9 Iran-U.S. Cl. Trib. Rep. 343 para. 100; Westinghouse Electric Corp., supra note 29, 33 Iran-U.S. Cl. Trib. Rep. 81 para. 64.
73CENTRAL-List Rule, reprinted in Berger, Creeping Codification, supra note 2, at p. 287, and Berger, "Introduction", supra note 4, at p. 160.
74Ultrasystems Inc. v. Islamic Republic of Iran, Award No. 27-84-3, 2 Iran-U.S. Cl. Trib. Rep. 100, 111 (4 March 1983); Benjamin R. Isaiah v. Bank Mellat, Award No. 35-219-2, 2 Iran-U.S. Cl. Trib. Rep. 232, 236-37 (30 March 1983); Sea-Land Service, Inc. v. Islamic Republic of Iran, Award No. 135-33-1, 6 Iran-U.S. Cl. Trib. Rep 149, 168-72 (22 June 1984); Morrison-Knudsen Pacific Ltd. v. Ministry of Roads and Transportation, Award No. 143-127-3, 7 Iran-U.S. Cl. Trib. Rep. 54, 76 (13 July 1984); DIC of Delaware, Inc. v. Tehran Redevelopment Corp., Award No. 176-255-3, 8 Iran-U.S. Cl. Trib. Rep. 144, 161-62 (26 April 1985); Futura Trading Inc. v. Khuzesran Water and Power Authority, Award No. 187-325-3, 9 Iran-U.S. Cl. Trib. Rep. 46, 57-58 (19 August 1985); Schlegel Corp. v. National Iranian Copper Industries Co., Award No. 295-834-2, 14 Iran-U.S. Cl. Trib. Rep. 176, 180-83 paras. 13-18 (27 March 1987); Mobil Oil Iran Inc., supra note 29, 16 Iran-U.S. Cl. Trib. Rep. 19 para. 54; Uiterwyk Corp. v. Islamic Republic of Iran, Award No. 375-381-1, 19 Iran-U.S. Cl. Trib. Rep. 107, 152 para. 157 (6 July 1988); Alfred Haber, P.A. v. Islamic Republic of Iran, Award No. 437-10159-3, 23 Iran-U.S. Cl. Trib. Rep. 133, 147 para. 58 (4 September 1989); W. Jack Buckameier, supra note 29, 28 Iran-U.S. Cl. Trib. Rep. 85-87 paras. 98-101. The Tribunal has rejected claims for unjust enrichment or quantum meruit in the following cases: Dames & Moore v. Islamic Republic of Iran, Award No. 97-54-3, 4 Iran-U.S. Cl. Trib. Rep. 212, 220-21 (20 December 1983); Morgan Equipment Co. v. Islamic Republic of Iran, Award No. 100-280-2, 4 Iran-U.S. Cl. Trib. Rep. 272, 278 (27 December 1983); T.C.S.B., Inc. v. Islamic Republic of Iran, Award No. 114-140-2, 5 Iran-U.S. Cl. Trib. Rep. 160, 171-72 (16 March 1984); Component Builders, Inc. v. Islamic Republic of Iran, Interim/Interlocutory Award No. ITM/ITL 51-395-3, 8 Iran-U.S. Cl. Trib. Rep. 216, 223-24 (27 May 1985); Shannon and Wilson, Inc. v. Atomic Energy Organization of Iran, Award No. 207-217-2, 9 Iran-U.S. Cl. Trib. Rep. 397, 402-3 paras. 20-22 (5 December 1985); Aeronutronic Overseas Services, Inc. v. Islamic Republic of Iran, Award No. 238-158-1, 11 Iran-U.S. Cl. Trib. Rep. 223, 238 para. 48 (20 June 1986); Flexi-Van Leasing, Inc. v. Islamic Republic of Iran, Award No. 259-36-1, 12 Iran-U.S. Cl. Trib. Rep. 335, 354-55 (13 October 1986); Futura Trading Inc. v. National Iranian Oil Co., Award No. 263-324-3, 13 Iran-U.S. Cl. Trib. Rep. 99, 115 para. 58, 117 para. 64 (30 October 1986); Reliance Group, Inc., supra note 29, 16 Iran-U.S. Cl. Trib. Rep. 272 para. 55; Lockheed Corp., supra note 29, 18 Iran-U.S. Cl. Trib. Rep. 309-10 para. 63; Rockwell International Systems, Inc., supra note 29, 23 Iran-U.S. Cl. Trib. Rep. 200 para. 190; Phibro Corp. v. Ministry of War-Etka Co. Ltd. Award No. 503-474-3, 26 Iran-U.S. Cl. Trib. Rep. 15, 27 paras. 48-49 (18 January 1991); Consortium for International Development v. Islamic Republic of Iran, Award No. 512-455-1, 26 Iran-U.S. Cl. Trib. Rep. 244, 251 para. 17 (15 May 1991); SeaCo, Inc. v. Islamic Republic of Iran, Award No. 531-260-2, 28 Iran-U.S. Cl. Trib. Rep. 198, 206-8 paras. 25-30 (25 June 1992). For a comprehensive discussion of the Tribunal's jurisprudence on unjust enrichment and quantum meruit, see Aldrich, supra note 6, at pp. 397-411.
75Brower & Brueschke, supra note 15, at p. 427.
76Consortium for International Development, supra note 74, 26 Iran-U.S. Cl. Trib. Rep. 251 para. 17. See also Dames & Moore, supra note 74, 4 Iran-U.S. Cl. Trib. Rep. 220-21; Component Builders, Inc., supra note 74, 8 Iran-U.S. Cl. Trib. Rep. 223-24.
77T.C.S.B. Inc., supra note 74, 5 Iran-U.S. Cl. Trib. Rep. 171. See also Aeronutronic Overseas Services, Inc., supra note 74, 11 Iran-U.S. Cl. Trib. Rep. 238 para. 48; Flexi-Van Leasing, Inc., supra note 74, 12 Iran-U.S. Cl. Trib. Rep. 353.
78Benjamin R. Isaiah, supra note 74, 2 Iran-U.S. Cl. Trib. Rep. 232.
79Article VII, para. 2, of the Claims Settlement Declaration provides that "[c]laims of nationals of Iran or the United States, as the case may be, means claims owned continuously, from the date on which the claim arose to the date on which this Agreement enters into force, by nationals of that state. ..." Claims Settlement Declaration, supra note 12, art. VII, para. 2.
80Benjamin R. Isaiah, supra note 74, 2 Iran-U.S. Cl. Trib. Rep. 236-37.
81Id. at p. 237.
82Id.
83Sea-Land Service, Inc., supra note 74, 6 Iran-U.S. Cl. Trib. Rep. 168. See also Flexi-Van Leasing, Inc., supra note 74, 12 Iran-U.S. Cl. Trib. Rep. 352-53.
84Sea-Land Service. Inc., supra note 74, 6 Iran-U.S. Cl. Trib. Rep. 169.
85Id.
86Id.
87See Morgan Equipment Co., supra note 74, 4 Iran-U.S. Cl. Trib. Rep. 278 (rejecting a claim based on unjust enrichment by an equipment supplier who shipped parts to a purchaser who was acting as a contractor, not an agent, for the Iranian Navy); Shannon and Wilson, Inc., supra note 74, 9 Iran-U.S. Cl. Trib. Rep. 402-3 paras 20-22 (rejecting a claim for lack of proof that the respondent had been unjustly enriched, but noting, in dicta, that, by contracting only with a third party, and not with the respondent, the claimant assumed the risk that the third party might not be able to collect all the funds it considered due from the respondent); SeaCo, Inc., supra note 74, 28 Iran-U.S. Cl. Trib. Rep. 206-8 paras 25-30 (denying a claim based on unjust enrichment for want of proof that the respondent's enrichment and the claimant's detriment arose as a consequence of the same act or event and distinguishing on the facts the Tribunal's award in Schlegel Corp., supra note 74).
88Schlegel Corp., supra note 74, 14 Iran-U.S. Cl. Trib. Rep. 182 para. 16.
89Id.
90Id. at pp. 182-83 para. 17.
91Id.
92See Ultrasystems Inc., supra note 74, 2 Iran-U.S. Cl. Trib. Rep. 111 (holding that the respondent's request for work, and the claimant's performance provided in accordance with that request, rendered the respondent liable at least in quantum meruit, without regard to the contract); Morrison-Knudsen Pacific Ltd.; supra note 74, 7 Iran-U.S. Cl. Trib. Rep. 76 (holding that the claimant was entitled to a reasonable sum as compensation in quantum meruit for additional work performed at the respondent's request where the contract provided that payment adjustments for extra services should be mutually agreed upon by the parties and where no such agreement was made); DIC of Delaware, Inc., supra note 74, 8 Iran-U.S. Cl. Trib. Rep. 161-62 (holding that the claimant was entitled to compensation in quantum meruit for work performend at the request and with the knowledge of the respondent, even though there was insufficient evidence that an enforceable contract had been signed).
93Id. at p. 162.
94The Tribunal's practice in unjust enrichment and quantum meruit cases to compensate claimants based on the extent to which the respondent state has been enriched stands in stark contrast to its practice in expropriation cases, where the Tribunal took the view that "compensation had to be measured by the loss to property owner rather than the gain, if any, by the expropriating State." Aldrich, supra note 6, at p. 227. In an early expropriation award, Tippetts, Abbett, McCarthy, Stratton v. TAMS-AFFA Consulting Engineers of Iran, the Tribunal stated with respect to the standard of compensation: The Claimant is entitled under international law and general principles of law to compensation for the full value of the property of which it was deprived. The Tribunal prefers the term "deprivation" to the term "taking," although they are largely synonymous, because the latter may be understood to imply that the Government has acquired something of value, which is not required. Tippetts, Abbett, McCarthy, Stratton v. TAMS-AFFA Consulting Engineers of Iran, Award No. 141-7-2, 6 Iran- U.S. Cl. Trib. Rep. 219, 225 (29 June 1984) (footnote omitted). See also Amoco International Finance Corp. v. Islamic Republic of Iran, Award No. 310-56-3, 15 Iran-U.S. Cl. Trib. Rep. 189, 269 para. 259 (14 July 1987) (rejecting the theory of unjust enrichment as an appropriate basis for compensation in expropriation cases).
95The CENTRAL-List unjust enrichment Rule provides that the value of the enrichment shall be determined "according to the contractually agreed price or market price, including full compensation for the use (usefruct) of the subject matter of the enrichment." Seetext accompanying note 73.
96Morrison-Knudsen Pacific Ltd., supra note 74, 7 Iran-U.S. Cl. Trib. Rep. 76.
97DIC of Delaware, Inc., supra note 74, 8 Iran-U.S. Cl. Trib. Rep. 162.
98Futura Trading Inc., supra note 74, 9 Iran-U.S. Cl. Trib. Rep. 57.
99Sea-Land Service, inc., supra note 74, 6 Iran-U.S. Cl. Trib. Rep. 196-71.
100See ibid. at p. 172. In a powerful dissent, Arbitrator Howard M. Holtzmann took issue with what he called the majority's "transmogrification"; of the measure of "actual benefit" into "actual use". Separate opinion of Howard M. Holtzmann, 6 Iran-U.S. Cl. Trib. Rep. 175, 215-16. He agreed that, in a situation where one party has been enriched at the expense of another in the absence of wrongdoing, it was "not a novelty" to measure compensation, not by injured party's loss, but rather by the enriched party's "actual benefit". Citing authority, he went on to say: "Actual benefit", however, has seldom if ever been equated with "actual use", the standard the Majority purports to apply. This is probably so because of the injustice that would result to the injured party if property with a determinable value could be cheapened by reference to the potentially wasteful or improvident uses to which it may be put by the party acquiring it. Another reason that an "actual use" standard has seldom if ever been adopted is its inherent difficulty in application. Evidence of "actual use"- if that is understood, as it is by the Majority, to mean the actual frequency of use given a piece of property- is almost always difficult to obtain and is generally available only to the respondent State. Thus, such evidence is actually lacking, as it is in the case. For this reason, even in this cases which mention the "use" by a respondent of the property at issue, the evidence has generally indicated- as in this case- only that the property had come into the respondent's hands and had been used to some extent by it. Having ascertained this fact, tribunals have not itemized and valued such "uses", but have awarded injured parties the value of the transferred property. Ibid. at pp. 213-14. In Mr. Holtzmann's view, the figure of USD 750000, which he stated the majority had pulled out of the air, was "derisory". Id. at p. 213.
101Flexi-Van Leasing, Inc., supra note 74, 12 Iran-U.S. Cl. Trib. Rep. 354. See also Dissenting Opinion of Howard M. Holtzmann in Flexi-Van Leasing, Inc., 12 Iran U.S. Cl. Trib. Rep. 356, 363 (stating, citing authority, that other international tribunals, rather than requiring proof of "actual use", have held that a benefit constituting unjust enrichment occurs when goods are available for use by a state, regardless of whether the claimant can show particular instances of that use).
102CENTRAL-List Rule, reprinted in Berger, Creeping Codification, supra note 2, at p. 295, and Berger, "Introduction", supra note 4, at p. 149.
103CENTRAL-List Rule, reprinted in Berger, Creeping Codification, supra note 2 at p. 295, and Berger, 'Introduction', supra note 4, at p. 148.
104Pomeroy Corp. v. Islamic Republic of Iran, Award No. 51-41-3, 2 Iran-U.S. Cl. Trib. Rep. 391, 397 (8 June 1983). See also RayGo Wagner Equipment Co. v. Star Line Iran Co., Award No. 20-17-3, Iran-U.S. Cl. Trib. Rep. 411, 413-14 (15 December 1982); Kimberly-Clark Corp. v. Bank Markazi Iran, Award No. 46-57-2, 2 Iran-U.S. Cl. Trib. Rep. 334, 339 (25 May 1983); R.N. Pomeroy v. Islamic Republic of Iran, Award No. 50-40-3, 2 Iran-U.S. Cl. Trib. Rep. 372-380 (8 June 1983); Chas. T. Main International, Inc. v. Khuzestan Water and Power Authority, Award No. ITL. 23-120-2, 3 Iran-U.S. Cl. Trib. Rep. 156, 163-64 (27 July 1983).
105Stephen G. Shifflette, supra note 29, 22 Iran-U.S. Cl. Trib. Rep. 115 para 18. See also DIC of Delaware, Inc., supra note 74, 8 Iran-U.S. Cl. Trib. Rep. 161 and Combustion Engineering, Inc., supra note 29, 26 Iran-U.S. Cl. Trib. Rep. 106 paras 161-63 (both holding that it is general principle of law that one can prove the existence of an enforceable contract through evidence demonstating part performance) and Woodward - Clyde Consultants v. Islamic Republic Iran, Award No. 73-67-3, 3 Iran-U.S. Cl. Trib. Rep. 239, 247 (2 September 1983) (holding that where the respondent orally consented to the claimant's services and paid for some of them, the respondent could not now avoid liability merely because neither party observed contract formalities').
106Intrend International, Inc. v. Imperial Iranian Air Force, Award No. 59-220-2, 3 Iran-U.S. Cl. Trib. Rep. 110, 115 (27 July 1983).
107General Dynamics Corp. v. Islamic Republic of Iran, Award No. 123-283-3, 5 Iran-U.S. Cl. Trib. Rep. 386, 394-95 (16 April 1984). Other cases in which the Tribunal has relied on the contemporaneous conduct of the parties in deciding questions of formation, validity, and interpretation of contracts include: Computer Sciences Corp., supra note 29, 10 Iran-U.S. Cl. Trib. Rep. 283; Reading and Bates Drilling Co. v. Islamic Republic of Iran, Award No. 355-10633-2, 18 Iran-U.S. Cl. Trib. Rep. 164, 172 para. 20 (16 March 1988); Seismograph Service Corp. v. National Iranian Oil Co., Award No. 420-443-3, 22 Iran-U.S. Cl. Trib. Rep. 3, 16 paras 41-42 (31 March 1989).
108Rexnord Inc. v. Islamic Republic of Iran, Award No. 21-132-3, 2 Iran-U.S. Cl. Trib. Rep. 6, 12 (10 January 1983). See also Westinghouse Electric Corp., supra note 29, 33 Iran-U.S. Cl. Trib. Rep. 154 para. 317 (rejecting for want of proof a claim that the claimant had charged exorbitant prices for spare parts on the ground that the respondent, as late as 1979, long after it had complained to the claimant about the prices, paid a number of the claimant's spares invoices).
109See John Carl Warnecke and Associates v. Bank Mellat, Award No. 72-124-3, 3 Iran-U.S. Cl. Trib. Rep 256, 261 (2 September 1983). Other cases in which the Tribunal has given significant weight to a party's failure to raise contemporaneous complaints include: Gould Marketing, Inc. (Final Award), supra note 45, 6 Iran-U.S. Cl. Trib. Rep. 277; Harnischfeger Corp. v. Ministry of Roads and Transportation, Award No. 144-180-3, 7 Iran-U.S. Cl. Trib. Rep. 90, 103 (13 July 1984);Blount Brothers Corp., supra note 47, 10 Iran-U.S. Cl. Trib. Rep. 67; The Trustees of Columbia University in the City of New York v. Islamic Republic of Iran, Award No. 222-10517-1, 10 Iran-U.S. Cl. Trib. Rep. 319, 326 para. 30 (16 April 1986); Logos Development Corp. v. Information Systems Iran of the Islamic Republic of Iran, Award No. 228-487-3, 11 Iran-U.S. Cl. Trib. Rep. 53, 65 para. 50 (30 April 1986), Mc Laughlin Enterprises, Ltd. v. Islamic Republic of Iran, Award No. 253-289-1, 12 Iran-U.S. Cl. Trib. Rep. 146, 150-51 para. 16 (16 September 1986); Ford Aerospace and Communications Corp., supra note 29, 14 Iran-U.S. Cl. Trib. Rep. 36, para. 47; Seismograph Service Corp., supra note 107, 22 Iran-U.S. Cl. Trib. Rep. 53-54 para. 193, 83 para. 320; Anaconda Iran, Inc. v. Islamic Republic of Iran, Final Award No. 539-167-3, 29 Iran-U.S. Cl. Trib. Rep. 320, 341-42 paras. 64-65, 367 para. 119 (29 October 1992); Westinghouse Electrc Corp., supra note 29, 33 Iran-U.S. Cl. Trib. Rep. 89 para 91. See also infra notes 117 and 118.
110Collins Systems International ,Inc., supra note 29, 28 Iran-U.S. Cl. Trib. Rep. 31 para. 29. See also ibid. at p. 32 para 34 (While the Tribunal has not considered itself bound by the parties' view as to whether a contract terminated, ... it has generally taken into account contemporaneous behavior in deciding that question'). Accord Westinghouse Electric Corp., supra note 29, 33 Iran U-S. Cl. Trib. Rep. 78 para. 53. See also Itel International Corp. v. Social Security Organization of Iran, Award No. 479-476-2, 24 Iran-U.S. Cl. Trib. Rep. 272, 283 para. 38 (23 May 1990); General Electric Co., supra note 29, 26 Iran-U.S. Cl. Trib. Rep. 158-61 paras. 32-40.
111Westinghouse Electric Corp., supra note 29, 33 Iran-U.S. Cl. Trib. Rep. 137. See also ibid. at p. 169 para. 360, 175 para. 379. The Tribunal applied similar reasoning in General Dynamics Telephone Systems Center, Inc., supra note 29, 9 Iran-U.S. Cl. Trib Rep. 159-60. See also Kimberly-Clark Corp., supra note 104, 2 Iran-U.S. Cl. Trib. Rep. 341-42.
112See Oil Field of Texas, Inc. v. Islamic Republic of Iran, Award No. 258-43-1, 12 Iran U.S. Cl. Trib. Rep. 308317 para. 35 (8 October 1986).
113Combustion Engineering, Inc., supra note 29, 26 Iran-U.S. Cl. Trib. Rep. 125-26 para. 240.
114Collins Systems International, Inc. supra note 29, 28 Iran-U.S. Cl. Trib. Rep. 39 para. 59. Cases in which the Tribunal has held that a party had waived a contractual right include: Lischem Corp. v. Atomic Energy Organization of Iran, Award No. 140-194-2, 7 Iran-U.S. Cl. Trib. Rep. 18, 23 (29 June 1984); Blount Brothers Corp., supra note 47, 10 Iran-U.S. Cl. Trib. Rep. 68; Logos Development Corp., supra note 109, 11 Iran-U.S. Cl. Trib. Rep. 64 para. 43; Howard Needles Tammen and Bergendoff v. Islamic Republic of Iran, Award No. 244-68-2, 11 Iran-U.S. Cl. Trib. Rep. 302, 330-31 paras. 105-107 (8 August 1986); Onesco, Inc. v. National Iranian Gas Co., Award No. 254-263-2, 12 Iran-U.S. Cl. Trib. Rep. 160, 167 para. 21 (18 September 1986); Cosmos Engineering, Inc. v. Ministry of Roads and Transportation, Award No. 271-334-2, 13 Iran-U.S. Cl. Trib. Rep. 179, 184-85 paras. 20-21 (24 November 1986); Whittaker Corp. v. Islamic Republic of Iran, award No. 301-286-1, 14 Iran-U.S. Cl. Trib. Rep. 263, 269-70 paras. 25-26 (27 April 1987). See also Phillips Petroleum Co. Iran v. Islamic Republic of Iran, Award No. 425-39-2, 21 Iran-U.S. Cl. Trib. Rep. 79, 155-56 paras. 198-99 (29 June 1989). Cases in which Tribunal has found that a party had not waived its contractual rights include General Dynamics Telephone Systems Center, Inc., supra note 29, 9 Iran-U.S. Cl. Trib. Rep. 162-63 and Unidyne Corp., supra note 29, 29 Iran-U.S. Cl. Trib. Rep. 326 para. 48.
115See, e.g. R.J. Reynolds Tobacco Co. v. Islamic Republic of Iran, Award No. 145-35-5, 7 Iran-U.S. Cl. Trib. Rep. 181, 190-91 (6 August 1984); DIC of Delaware, Inc., supra note 74, 8 Iran-U.S. Cl. Trib. Rep. 164; Sylvania Technical Systems, Inc., supra note 29, 8 Iran-U.S. Cl. Trib. Rep. 316; Questech, Inc., supra note 29, 9 Iran-U.S. Cl. Trib. Rep. 126; Touche Ross and Co., supra note 29, 9 Iran-U.S. Cl. Trib. Rep 298; Ford Aerospace and Communications Corp., supra note 29, 14 Iran-U.S. Cl. Trib. Rep. 41 para. 62; Harris International Telecommunications, Inc., supra note 29, 17 Iran-U.S. Cl. Trib. Rep. 73 para. 143; Houston Contracting Co., supra note 29, 20 Iran-U.S. Cl. Trib. Rep. 24-25 para. 73; Rockwell International Systems, Inc., supra note 29, 23 Iran-U.S. Cl. Trib. Rep. 183 para. 127, 188 para. 188; Collins Systems International, Inc., supra note 29, 28 Iran-U.S. 38-39 para. 57; Westinghouse Electric Corp., supra note 29, 33 Iran-U.S. Cl. Trib. Rep. 113 para. 164, 180-81 paras. 394-95; Gulf Associates, Inc. v. Islamic Republic of Iran, Award No. 594-385-2, para. 127 (7 October 1999) (not yet published in the Iran-U.S. Claims Tribunal Reports).
116See Westinghouse Electric corp., supra note 29, 33 Iran-U.S. Cl. Trib. Rep. 180-81 paras. 394-95.
117See, e.g., Richard D. Harza, supra note 29, 11 Iran-U.S. Cl. Trib. Rep. 114 para. 99; The Austin Co. v. Machine Sazi Arak, Award No. 257-295-2, 12 Iran-U.S Cl. Trib. Rep. 288, 294-95 paras. 31-32 (30 September 1986); Westinghouse Electric Corp., supra note 29, 33 Iran-U.S. Cl. Trib. Rep. 105-6 para. 141; 139-40 para 271.
118DIC of Delaware, Inc., supra note 74, 8 Iran-U.S. Cl. Trib. Rep. 176.
119It would extend beyond the scope of this article to explore whether the Tribunal, in its jurisprudence, has also developed any rules that now or in the future may be included in the body of the lex mercatoria. Berger describes this sort of evolution process as the 'development of individual rules from mere candidates to genuine components of die lex mercatoria.' Berger, Introduction, supra note 4, at p. 140 (footnote omitted). See also ibid. at pp. 140-44. On a related note, Crook writes that '[i]t would be useful to analyze the tribunal's contract cases in greater detail, to further examine key principles to be refined and appliecl in the future.' Crook, 'Debt and Contract Claims', supra note 22, at p. 300.
120Brower and Brueschke., supra note 15, at p. 669.
121Claims Settlement Declaration, supra note 12, article V. See text accompanying note 20.
27CENTRAL-List Rule, reprinted in Berger, Creeping Codification, supra note 2, at p. 288, and Berger, Introduction, supra note 4, at pp. 156-157.
28For a comprehensive discussion of the Tribunal's jurisprudence in force majeure cases, see Aldrich, supra note 6, at pp. 306-320.
29Gould Marketing, Inc. v. Ministry of National Defense of lran, Interlocutory Award No. ITL 24-49-2, 3 Iran-U.S. Cl. Trib. Rep. 147, 152-53 (27 July 1983); Starrett Housing Corp. v. Islamic Republic of Iran, Interlocutory Award No. ITL 32-24-1, 4 Iran-U.S. Cl. Trib. Rep. 122, 155 (19 December 1983); Department of the Environment of the Islamic Republic of Iran v. United States of America, Award No. 107-B53-1, 5 Iran-U.S. Cl. Trib. Rep. 105, 110 (25 January 1984); Sylvania Technical Systems, Inc. v. Islamic Republic of Iran, Award No. 180-64-1, 8 Iran-U.S. Cl. Trib. Rep. 298, 308-9 (27 June 1985); International Technical Products Corp. v. Islamic Republic of Iran, Award No. 186-302-3, 9 Iran-U.S. Cl. Trib. Rep. 10, 23-24 (19 August 1985); Questech, Inc. v. Ministry of National Defense of the Islamic Republic of Iran, Award No. 191-59-1, 9 Iran-U.S. Cl. Trib. Rep. 107, 119 (25 September 1985); General Dynamics Telephone Systems Center, Inc. v. Islamic Republic of Iran, Award No. 192-285-2, 9 Iran-U.S. Cl. Trib. Rep. 153, 160 (4 October 1985); International Schools Services, Inc. v. National Iranian Copper Industries Co., Award No. 194-111-1, 9 Iran-U.S. Cl. Trib. Rep. 187, 196 (10 October 1985) ("International School Services I"); Touche Ross and Co. v. Islamic Republic of Iran, Award No. 197-480-1, 9 Iran-U.S. Cl. Trib. Rep. 284, 294-95 (30 October 1985); Phelps Dodge International Corp. v. Islamic Republic of Iran, Award No. 218-135-2, 10 Iran-U.S. Cl. Trib. Rep. 157, 173 para. 51 (19 March 1986); Computer Sciences Corp. v. Islamic Republic of Iran, Award No. 221-65-1, 10 Iran-U.S. Cl. Trib. Rep. 269, 289 (16 April 1986); Richard D. Harza v. Islamic Republic of Iran, Award No. 232-97-2, 11 Iran-U.S. Cl. Trib. Rep. 76, 91 para. 37 (2 May 1986); Ammann & Whitney v. Ministry of Housing and Urban Development, Award No. 248-198-1, 12 Iran-U.S. Cl. Trib. Rep. 94, 104 (25 August 1986); American Bell International Inc. v. Islamic Republic of Iran, Award No. 255-48-3, 12 Iran-U.S. Cl. Trib. Rep. 170, 184 para. 47 (19 September 1986); Henry, F. Teichmann, Inc. v. Hamadan Glass Co., Award No. 264-264-1, 13 Iran-U.S. Cl. Trib. Rep. 124, 133 paras. 31-32 (12 November 1986); Anaconda Iran, Inc. v. Islamic Republic of Iran, Interlocutory Award No. ITL 65-167-3, 13 Iran-U.S. Cl. Trib. Rep. 199, 212-13 paras. 47-50 (10 December 1986); Ford Aerospace & Communications Corp. v. Islamic Republic of Iran, Award No. 289-93-1, 14 Iran-U.S. Cl. Trib. Rep. 24, 35-36 paras. 45-46 (29 January 1987); International Schools Services, Inc. v. Islamic Republic of Iran, Award No. 290-123-1, 14 Iran-U.S. Cl. Trib. Rep. 65, 73 para. 27 (29 January 1987) ("International School Services II"); Exxon Research and Engineering Co. v. National Iranian Oil Co., Award No. 308-155-3, 15 Iran-U.S. Cl. Trib. Rep. 3, 11 para. 30 (9 June 1987); Reliance Group, Inc. v. Oil Service Company of Iran, Award No. 315-115-3, 16 Iran-U.S. Cl. Trib. Rep. 257, 269-71, paras. 46, 51 (10 September 1987); Mobil Oil Iran Inc. v. Islamic Republic of Iran, Award No. 311-74/76/81/150-3, 16 Iran-U.S. Cl. Trib. Rep. 3, 38-39 paras. 114-17 (14 July 1987); Harris International Telecommunications, Inc. v. Islamic Republic of Iran, Award No. 323-409-1, 17 Iran-U.S. Cl. Trib. Rep. 31, 67 paras. 121-22 (2 November 1987); Lockheed Corp. v. Islamic Republic of Iran, Award No. 367-829-2, 18 Iran-U.S. Cl. Trib. Rep. 292, 302 para. 40 (9 June 1988); Motorola, Inc. v. Iran National Airlines Corp., Award No. 373-481-3, 19 Iran-U.S. Cl. Trib. Rep. 73, 80 para. 36, 85 para. 56 (28 June 1988); Avco Corp. v. Iran Aircraft Industries, Award No. 377-261-3, 19 Iran-U.S. Cl. Trib. Rep. 200, 216-17 paras. 79-80 (18 July 1988); Houston Contracting Co. v. National Iranian Oil Co., Award No. 378-173-3, 20 Iran-U.S. Cl. Trib. Rep. 3, 28 para. 87, 48-49 paras. 155-57 (22 July 1988); Stephen G. Shifflette v. Islamic Republic of Iran, Award No. 423-10645-1, 22 Iran-U.S. Cl. Trib. Rep. 111, 115-16 para. 19 (12 June 1989); Watkins-Johnson Co. v. Islamic Republic of Iran, Award No. 429-370-1, 22 Iran-U.S. Cl. Trib. Rep. 218, 242 para. 89 (28 July 1989); Electronic Systems International, Inc. v. Ministry of Defense of the Islamic Republic of Iran, Award No. 430-814-1, 22 Iran-U.S. Cl. Trib. Rep. 339, 355 para. 61 (28 July 1989); Rockwell International Systems, Inc. v. Islamic Republic of Iran, Award No. 438-430-1, 23 Iran-U.S. Cl. Trib. Rep. 150, 170 para. 88 (5 September 1989); Combustion Engineering, Inc. v. Islamic Republic of Iran, Award No. 506-308-2, 26 Iran-U.S. Cl. Trib. Rep. 60, 77 para. 61, 80 para. 71 (18 February 1991); General Electric Co. v. Islamic Republic of Iran, Award No. 507-386-1, 26 Iran-U.S. Cl. Trib. Rep. 148, 180 para. 111 (15 March 1991); Petrolane, Inc. v. Islamic Republic of Iran, Award No. 518-131-2, 27 Iran-U.S. Cl. Trib. Rep. 64, 80-81 paras. 48-51 (14 August 1991); William J. Levitt v. Islamic Republic of Iran, Award No. 520-210-3, 27 Iran-U.S. Cl. Trib. Rep. 145, 166-67 para. 71 (29 August 1991); Collins Systems International, Inc. v. Navy of the Islamic Republic of Iran, Award No. 526- 431-2, 28 Iran U.S. Cl. Trib. Rep. 21, 35 para. 43 (20 January 1992); W. Jack Buckameier v. Islamic Republic of Iran, Award No. 528-941-3, 28 Iran-U.S. Cl. Trib. Rep. 53, 84-85 para. 95 (6 March 1992); Unidyne Corp. v. Islamic Republic of Iran, Award No. 551-368-3, 29 Iran-U.S. Cl. Trib. Rep. 310, 340-42 paras. 94-97 (10 November 1993); Westinghouse Electric Corp. v. Islamic Republic of Iran Air Force, Award No. 579-389-2, 33 Iran-U.S. Cl. Trib. Rep. 60, 78 para. 54, 80 paras. 60-61 (26 March 1997); Bank Markazi Iran v. The Federal Reserve Bank of New York, Award No. 595-823-3, para. 75 (16 November 1999) (not yet published in the Iran-U.S. Claims Tribunal Reports).
30See, e.g., Anaconda Iran, Inc., supra note 29, 13 Iran-U.S. Cl. Trib. Rep. 211 para. 43 ("Under a variety of names most, if not all, legal systems recognize force majeure as an excuse for contractual non-performance. Force majeure therefore can be considered a general principle of law"); Mobil Oil Iran Inc., supra note 29, 16 Iran-U.S. Cl. Trib. Rep. 39 para. 117.
31Anaconda Iran Inc., supra note 29, 13 Iran-U.S. Cl. Trib. Rep. 211 para. 43. See also Mobil Oil Iran Inc., supra note 29, 16 Iran-U.S. Cl. Trib. Rep. 39 para. 117 (force majeure is a general principle of law that applies "even when the contract is silent").
32Gould Marketing, Inc. (Interlocutory Award), supra note 29, 3 Iran-U.S. Cl. Trib. Rep. 147.
33Id. at pp. 152-53.
34Sylvania Technical Systems, Inc. supra, note 29, 8 Iran-U.S. Cl. Trib. Rep. 298.
35Id. at p. 309.
36Id. at p. 312.
37See text accompanying note 33.
38Sylvania Technical Systems, Inc., supra note 29, 8 Iran-U.S. Cl. Trib. Rep. 309-10.
39Id. at p. 312. In rejecting the respondent's plea of force majeure, the Tribunal noted that the Iranian government had terminated the contract at issue as a result of a "deliberate policy decision not to continue with American contractors in a project that related to secret military intelligence operations" and that such a decision had been taken in view of an historic development, and do[es] not convey that performance by the [respondent] was prevented by events beyond its control. Id. at pp. 312-13.
40International Technical Products Corp., supra note 29, 9 Iran-U.S. Cl. Trib. Rep. 24.
41See ibid.
42Starrett Housing Corp., supra note 29, 4 Iran-U.S. Cl. Trib. Rep. 155.
43International Technical Products Corp., supra note 29, 9 Iran-U.S. Cl. Trib. Rep. 24.
44On 14 November 1979, US President Carter imposed economic sanctions on Iran in response to the 4 November seizure of the United States Embassy in Tehran. See text accompanying note 8.
45See, e.g., Gould Marketing, Inc. v. Ministry of National Defense of Iran, Final Award No. 136-49/50-2, 6 Iran-U.S. Cl. Trib. Rep. 272, 279 (29 June 1984); Avco Corp., supra note 29, 19 Iran-U.S. Cl. Trib. 216-17 paras. 79-80; Collins Systems International, Inc., supra note 29, 28 Iran-U.S. Cl. Trib. Rep. 35 para. 43; Unidyne Corp., supra note 29, 29 Iran-U.S. Cl. Trib. Rep. 342 para. 97.
46See e.g., Gould Marketing, Inc. (Final Award), supra note 45, 6 Iran-U.S. Cl. Trib. Rep. 279; Westinghouse Electric Corp., supra note 29, 33 Iran-U.S. Cl. Trib. Rep. 171-72 paras. 367-68.
47Blount Brothers Corp. v. Islamic Republic of Iran, Award No. 215-52-1, 10 Iran-U.S. Cl. Trib. Rep. 56 (6 March 1986).
48The question of the invocation of force majeure by a government agency for actions by its own government has been the subject of much debate. See, e.g., Karl-Heinz Böckstiegel, Arbitration and State Enterprises (Kluwer Law and Taxation Publisher, Deventer/Antwerp/Boston/Frankfurt/London, 1984) at pp. 37-39; Georges R. Delaume Law and Practice of Transnational Contracts (Oceans Publications Inc., New York/London/Rome 1988) at pp. 54-57; Thomas E. Carbonneau, "The Elaboration of Substantive Legal Norms and Arbitral Adjudication: The Case of the Iran-United States Claims Tribunal" in The Iran-United States Claims Tribunal 1981-1983 - Seventh Sokol Colloquium (ed. Richard B. Lillich) (University Press of Virginia Charlottesville, 1984) at pp. 104, 116-17, 120.
49Blount Brothers Corp., supra note 47, 10 Iran-U.S. Cl. Trib. Rep. 75. See also Bank Markazi Iran, supra note 29, at paras. 75-76 (holding, even if the Federal Reserve Bank of New York were considered an entity controlled by the government of the United States, it could, in the circumstances, invoke force majeure since it has its own legal personality distinct from the state). Accord C. Czarnikow Ltd. v. Centrala Handlu Zagranieznego Rolimpex, 1979 A.C. 351, discussed in Delaume, supra note 48, at p. 55, and Carbonneau, supra note 48, at pp. 116-17.
50See, e.g., Gould Marketing. Inc. (Interlocutory Award), supra note 29, 3 Iran-U.S. Cl. Trib. Rep. 153; Sylvania Technical Systems, Inc., supra note 29, 8 Iran-U.S. Cl. Trip. Rep. 309-10; Anaconda Iran, Inc., supra note 29, 13 Iran-U.S. Cl. Trib. Rep. 211 para. 41; General Electric Co., supra note 29, 26 Iran-U.S. Cl. Trib. Rep. 180 para. 111; Westinghouse Electric Corp., supra note 29, 33 Iran-U.S. Cl. Trib. Rep. 78 para. 54.
51The CENTRAL-List force majeure Rule provides that the affected party's "non-performance is excused" and that, "[i]f non-performance is temporary, performance of the contract is suspended during that time". See text accompanying note 27.
52See supra notes 29 and 32.
53Gould Marketing, Inc. (Interlocutory Award), supra note 29, 3 Iran-U.S. Cl. Trib. Rep. 154.
54See, e.g., International Schools Services I, supra note 29, 9 Iran-U.S. Cl. Trib. Rep. 196; Anaconda Iran, Inc., supra note 29, 13 Iran-U.S. Cl. Trib. Rep. 211 para. 41; International Schools Services II, supra note 29, 14 Iran-U.S. Cl. Trib. Rep. 72-73 paras. 23, 27; Mobil Oil Iran Inc., supra note 29, 16 Iran-U.S. Cl. Trib. Rep. 39 para. 117; Stephen G. Shifflette, supra note 29, 22 Iran-U.S. Cl. Trib. Rep. 15-16 para. 19; Combustion Engineering, Inc., supra note 29, 26 Iran-U.S. Cl. Trib. Rep. 77 para 61, 80 para. 71, 116 para. 207; William, J. Levitt, supra note 29, 27 Iran-U.S. Cl Trib. Rep. 166-67 para. 71; Unidyne Corp., supra note 29, 29 Iran-U.S. Cl. Trib. Rep. 342 paras. 97-98; Westinghouse Electric Corp., supra note 29, 33 Iran-U.S. Cl. Trib. Rep. 80 para. 61, 136 para. 259, 169 para. 360, 175 para. 379. See also Queens Office Tower Associates v. Iran National Airlines Corp., Award No. 37-172-1, 2 Iran-U.S. Cl. Trib. Rep 247, 251-52 (15 April 1983) (finding that an Iran Air lease of certain office commercial space in New York had been subject to a "combination of frustration of purpose and impossibility of payment" due to United States economic sanctions against Iran); Linen, Fortinberry and Associates, Inc. v. Islamic Republic of Iran, Award No. 372-10513-2, 19 Iran-U.S. Cl. Trib. Rep. 62, 70 para. 28 (28 June 1988) (holding that the purpose of a contract pursuant to which an American public relations firm was to promote the public image in the United States of the Pahlavi dynasty's Iran was frustrated by the success of the Islamic Revolution).
55The CENTRAL-List force majeure Rule, however, does deal with the situation where continued suspension of contractual performance becomes attributable to one of the parties: "If the period of non-performance becomes unreasonable and amounts to a fundamental non-performance, the other party may claim damages and terminate the contract." See text accompanying note 27.
56See supra note 54.
57See John A. Westberg, International Transactions and Claims Involving Government Parties - Case Law of the Iran-United States Claims Tribunal (International Law Institute, Washington D.C., 1991) at pp. 168-71, 182; Crook, "Debt and Contract Claims", supra note 22, at pp. 288-290; Crook, "Applicable Law", supra note 22, at p. 294.
58Sylvania Technical Systems, Inc., supra note 29, 8 Iran-U.S. Cl. Trib. Rep. 309, and text accompanying note 35 ("Sylvania-test").
59Westberg, supra note 57, at p. 182.
60See Sylvania Technical Systems, Inc., supra note 29, 8 Iran-U.S. CL. Trib. Rep. 308-10, 312-13, and supra note 39.
61Gould Marketing, Inc. (Interlocutory Award), supra note 29, 3 Iran-U.S. Cl. Trib. Rep. 153.
62Ibid.
63Ibid.
64See ibid. at p. 154.
65Sylvania-test, see supra note 58.
66Queens Office Tower Associates, supra note 54, 2 Iran-U.S. Cl. Trib. Rep. 254.
67Gould Marketing, Inc. (Final Award), supra note 45, 6 Iran-U.S. Cl. Trib. Rep. 274 (footnote omitted).
68See International School Services I, supra note 29, 9 Iran-U.S. Cl. Trib. Rep. 196-97; Phelps Dodge International Corp., supra note 29, 10 Iran-U.S. Cl. Trib. Rep. 173 para. 52; International Schools Services II, supra note 29, 14 Iran-U.S. Cl. Trib. Rep. 73-74 para. 30; William J. Levitt, supra note 29, 27 Iran-U.S. Cl. Trib. Rep. 167-68 paras. 74-76; Unidyne Corp., supra note 29, 29 Iran-U.S. Cl. Trib. Rep. 342-43 para. 99; Westinghouse Electric Corp., supra note 29, 33 Iran-U.S. Cl. Trib. Rep. 80-81 paras. 63-64. In Westinghouse Electric Corp., ibid. at p. 81 para. 64, the Tribunal set forth in clear and simple terms how it would determine who owed what to whom as a result of the frustration of the contracts at issue: "[The Tribunal] will determine the extent to which [the claimant] performed its obligations under each ... contract ... until such performance was made impossible, and whether, based on such performance, [the claimant] is entitled to receive further payments or, on the contrary, must return to the [respondent] part of the payments it received." See also Lockheed Corp., supra note 29, 18 Iran-U.S. Cl. Trib. Rep. 303 para. 40 (holding that whether a contract is considered ultimately frustrated or expired by its own terms makes no difference in the settlement of accounts between the parties and the determination of what one owes to whom).
69See, e.g., International School Services I, supra note 29, 9 Iran-U.S. Cl. Trib. Rep. 197-99 (awarding costs incurred prior to the date of termination of a contract to operate a school for American children in Iran, but rejecting claims for costs incurred after such date, including transportation and moving expenses, and for lost profits); Stephen G. Shifflette, supra note 29, 22 Iran-U.S. Cl. Trib. Rep. 115-16 para. 19 (awarding compensation for the two weeks the claimant worked pursuant to a contract for teaching services in Iran, but not lost wages for the remainder of the semester); Combustion Engineering, Inc., supra note 29, 26 U.S. Cl. Trib. Rep. 77 paras. 62, 207 (dismissing claims for licence fees due subsequent to the termination of the licensing agreement); Unidyne Corp., supra note 29, 29 Iran-U.S. Cl. Trib. Rep. 344 paras. 102-103 (awarding compensation for work performed but not paid for, but denying a claim for lost profits); Westinghouse Electric Corp., supra note 29, 33 Iran-U.S. Cl. Trib. Rep. 81 para. 64, 126 para. 216 (awarding compensation for work performed but not paid for, but denying claim for lost profits).
70Westinghouse Electric Corp., supra note 29.
71Id. 33 Iran-U.S. Cl. Trib. Rep. 80 para. 62; International Schools Services I, supra note 29, 9 Iran-U.S. Cl. Trib. Rep. 196-97.
72See, e.g. Unidyne Corp., supra note 29, 9 Iran-U.S. Cl. Trib. Rep. 343 para. 100; Westinghouse Electric Corp., supra note 29, 33 Iran-U.S. Cl. Trib. Rep. 81 para. 64.
73CENTRAL-List Rule, reprinted in Berger, Creeping Codification, supra note 2, at p. 287, and Berger, "Introduction", supra note 4, at p. 160.
74Ultrasystems Inc. v. Islamic Republic of Iran, Award No. 27-84-3, 2 Iran-U.S. Cl. Trib. Rep. 100, 111 (4 March 1983); Benjamin R. Isaiah v. Bank Mellat, Award No. 35-219-2, 2 Iran-U.S. Cl. Trib. Rep. 232, 236-37 (30 March 1983); Sea-Land Service, Inc. v. Islamic Republic of Iran, Award No. 135-33-1, 6 Iran-U.S. Cl. Trib. Rep 149, 168-72 (22 June 1984); Morrison-Knudsen Pacific Ltd. v. Ministry of Roads and Transportation, Award No. 143-127-3, 7 Iran-U.S. Cl. Trib. Rep. 54, 76 (13 July 1984); DIC of Delaware, Inc. v. Tehran Redevelopment Corp., Award No. 176-255-3, 8 Iran-U.S. Cl. Trib. Rep. 144, 161-62 (26 April 1985); Futura Trading Inc. v. Khuzesran Water and Power Authority, Award No. 187-325-3, 9 Iran-U.S. Cl. Trib. Rep. 46, 57-58 (19 August 1985); Schlegel Corp. v. National Iranian Copper Industries Co., Award No. 295-834-2, 14 Iran-U.S. Cl. Trib. Rep. 176, 180-83 paras. 13-18 (27 March 1987); Mobil Oil Iran Inc., supra note 29, 16 Iran-U.S. Cl. Trib. Rep. 19 para. 54; Uiterwyk Corp. v. Islamic Republic of Iran, Award No. 375-381-1, 19 Iran-U.S. Cl. Trib. Rep. 107, 152 para. 157 (6 July 1988); Alfred Haber, P.A. v. Islamic Republic of Iran, Award No. 437-10159-3, 23 Iran-U.S. Cl. Trib. Rep. 133, 147 para. 58 (4 September 1989); W. Jack Buckameier, supra note 29, 28 Iran-U.S. Cl. Trib. Rep. 85-87 paras. 98-101. The Tribunal has rejected claims for unjust enrichment or quantum meruit in the following cases: Dames & Moore v. Islamic Republic of Iran, Award No. 97-54-3, 4 Iran-U.S. Cl. Trib. Rep. 212, 220-21 (20 December 1983); Morgan Equipment Co. v. Islamic Republic of Iran, Award No. 100-280-2, 4 Iran-U.S. Cl. Trib. Rep. 272, 278 (27 December 1983); T.C.S.B., Inc. v. Islamic Republic of Iran, Award No. 114-140-2, 5 Iran-U.S. Cl. Trib. Rep. 160, 171-72 (16 March 1984); Component Builders, Inc. v. Islamic Republic of Iran, Interim/Interlocutory Award No. ITM/ITL 51-395-3, 8 Iran-U.S. Cl. Trib. Rep. 216, 223-24 (27 May 1985); Shannon and Wilson, Inc. v. Atomic Energy Organization of Iran, Award No. 207-217-2, 9 Iran-U.S. Cl. Trib. Rep. 397, 402-3 paras. 20-22 (5 December 1985); Aeronutronic Overseas Services, Inc. v. Islamic Republic of Iran, Award No. 238-158-1, 11 Iran-U.S. Cl. Trib. Rep. 223, 238 para. 48 (20 June 1986); Flexi-Van Leasing, Inc. v. Islamic Republic of Iran, Award No. 259-36-1, 12 Iran-U.S. Cl. Trib. Rep. 335, 354-55 (13 October 1986); Futura Trading Inc. v. National Iranian Oil Co., Award No. 263-324-3, 13 Iran-U.S. Cl. Trib. Rep. 99, 115 para. 58, 117 para. 64 (30 October 1986); Reliance Group, Inc., supra note 29, 16 Iran-U.S. Cl. Trib. Rep. 272 para. 55; Lockheed Corp., supra note 29, 18 Iran-U.S. Cl. Trib. Rep. 309-10 para. 63; Rockwell International Systems, Inc., supra note 29, 23 Iran-U.S. Cl. Trib. Rep. 200 para. 190; Phibro Corp. v. Ministry of War-Etka Co. Ltd. Award No. 503-474-3, 26 Iran-U.S. Cl. Trib. Rep. 15, 27 paras. 48-49 (18 January 1991); Consortium for International Development v. Islamic Republic of Iran, Award No. 512-455-1, 26 Iran-U.S. Cl. Trib. Rep. 244, 251 para. 17 (15 May 1991); SeaCo, Inc. v. Islamic Republic of Iran, Award No. 531-260-2, 28 Iran-U.S. Cl. Trib. Rep. 198, 206-8 paras. 25-30 (25 June 1992). For a comprehensive discussion of the Tribunal's jurisprudence on unjust enrichment and quantum meruit, see Aldrich, supra note 6, at pp. 397-411.
75Brower & Brueschke, supra note 15, at p. 427.
76Consortium for International Development, supra note 74, 26 Iran-U.S. Cl. Trib. Rep. 251 para. 17. See also Dames & Moore, supra note 74, 4 Iran-U.S. Cl. Trib. Rep. 220-21; Component Builders, Inc., supra note 74, 8 Iran-U.S. Cl. Trib. Rep. 223-24.
77T.C.S.B. Inc., supra note 74, 5 Iran-U.S. Cl. Trib. Rep. 171. See also Aeronutronic Overseas Services, Inc., supra note 74, 11 Iran-U.S. Cl. Trib. Rep. 238 para. 48; Flexi-Van Leasing, Inc., supra note 74, 12 Iran-U.S. Cl. Trib. Rep. 353.
78Benjamin R. Isaiah, supra note 74, 2 Iran-U.S. Cl. Trib. Rep. 232.
79Article VII, para. 2, of the Claims Settlement Declaration provides that "[c]laims of nationals of Iran or the United States, as the case may be, means claims owned continuously, from the date on which the claim arose to the date on which this Agreement enters into force, by nationals of that state. ..." Claims Settlement Declaration, supra note 12, art. VII, para. 2.
80Benjamin R. Isaiah, supra note 74, 2 Iran-U.S. Cl. Trib. Rep. 236-37.
81Id. at p. 237.
82Id.
83Sea-Land Service, Inc., supra note 74, 6 Iran-U.S. Cl. Trib. Rep. 168. See also Flexi-Van Leasing, Inc., supra note 74, 12 Iran-U.S. Cl. Trib. Rep. 352-53.
84Sea-Land Service. Inc., supra note 74, 6 Iran-U.S. Cl. Trib. Rep. 169.
85Id.
86Id.
87See Morgan Equipment Co., supra note 74, 4 Iran-U.S. Cl. Trib. Rep. 278 (rejecting a claim based on unjust enrichment by an equipment supplier who shipped parts to a purchaser who was acting as a contractor, not an agent, for the Iranian Navy); Shannon and Wilson, Inc., supra note 74, 9 Iran-U.S. Cl. Trib. Rep. 402-3 paras 20-22 (rejecting a claim for lack of proof that the respondent had been unjustly enriched, but noting, in dicta, that, by contracting only with a third party, and not with the respondent, the claimant assumed the risk that the third party might not be able to collect all the funds it considered due from the respondent); SeaCo, Inc., supra note 74, 28 Iran-U.S. Cl. Trib. Rep. 206-8 paras 25-30 (denying a claim based on unjust enrichment for want of proof that the respondent's enrichment and the claimant's detriment arose as a consequence of the same act or event and distinguishing on the facts the Tribunal's award in Schlegel Corp., supra note 74).
88Schlegel Corp., supra note 74, 14 Iran-U.S. Cl. Trib. Rep. 182 para. 16.
89Id.
90Id. at pp. 182-83 para. 17.
91Id.
92See Ultrasystems Inc., supra note 74, 2 Iran-U.S. Cl. Trib. Rep. 111 (holding that the respondent's request for work, and the claimant's performance provided in accordance with that request, rendered the respondent liable at least in quantum meruit, without regard to the contract); Morrison-Knudsen Pacific Ltd.; supra note 74, 7 Iran-U.S. Cl. Trib. Rep. 76 (holding that the claimant was entitled to a reasonable sum as compensation in quantum meruit for additional work performed at the respondent's request where the contract provided that payment adjustments for extra services should be mutually agreed upon by the parties and where no such agreement was made); DIC of Delaware, Inc., supra note 74, 8 Iran-U.S. Cl. Trib. Rep. 161-62 (holding that the claimant was entitled to compensation in quantum meruit for work performend at the request and with the knowledge of the respondent, even though there was insufficient evidence that an enforceable contract had been signed).
93Id. at p. 162.
94The Tribunal's practice in unjust enrichment and quantum meruit cases to compensate claimants based on the extent to which the respondent state has been enriched stands in stark contrast to its practice in expropriation cases, where the Tribunal took the view that "compensation had to be measured by the loss to property owner rather than the gain, if any, by the expropriating State." Aldrich, supra note 6, at p. 227. In an early expropriation award, Tippetts, Abbett, McCarthy, Stratton v. TAMS-AFFA Consulting Engineers of Iran, the Tribunal stated with respect to the standard of compensation: The Claimant is entitled under international law and general principles of law to compensation for the full value of the property of which it was deprived. The Tribunal prefers the term "deprivation" to the term "taking," although they are largely synonymous, because the latter may be understood to imply that the Government has acquired something of value, which is not required. Tippetts, Abbett, McCarthy, Stratton v. TAMS-AFFA Consulting Engineers of Iran, Award No. 141-7-2, 6 Iran- U.S. Cl. Trib. Rep. 219, 225 (29 June 1984) (footnote omitted). See also Amoco International Finance Corp. v. Islamic Republic of Iran, Award No. 310-56-3, 15 Iran-U.S. Cl. Trib. Rep. 189, 269 para. 259 (14 July 1987) (rejecting the theory of unjust enrichment as an appropriate basis for compensation in expropriation cases).
95The CENTRAL-List unjust enrichment Rule provides that the value of the enrichment shall be determined "according to the contractually agreed price or market price, including full compensation for the use (usefruct) of the subject matter of the enrichment." Seetext accompanying note 73.
96Morrison-Knudsen Pacific Ltd., supra note 74, 7 Iran-U.S. Cl. Trib. Rep. 76.
97DIC of Delaware, Inc., supra note 74, 8 Iran-U.S. Cl. Trib. Rep. 162.
98Futura Trading Inc., supra note 74, 9 Iran-U.S. Cl. Trib. Rep. 57.
99Sea-Land Service, inc., supra note 74, 6 Iran-U.S. Cl. Trib. Rep. 196-71.
100See ibid. at p. 172. In a powerful dissent, Arbitrator Howard M. Holtzmann took issue with what he called the majority's "transmogrification"; of the measure of "actual benefit" into "actual use". Separate opinion of Howard M. Holtzmann, 6 Iran-U.S. Cl. Trib. Rep. 175, 215-16. He agreed that, in a situation where one party has been enriched at the expense of another in the absence of wrongdoing, it was "not a novelty" to measure compensation, not by injured party's loss, but rather by the enriched party's "actual benefit". Citing authority, he went on to say: "Actual benefit", however, has seldom if ever been equated with "actual use", the standard the Majority purports to apply. This is probably so because of the injustice that would result to the injured party if property with a determinable value could be cheapened by reference to the potentially wasteful or improvident uses to which it may be put by the party acquiring it. Another reason that an "actual use" standard has seldom if ever been adopted is its inherent difficulty in application. Evidence of "actual use"- if that is understood, as it is by the Majority, to mean the actual frequency of use given a piece of property- is almost always difficult to obtain and is generally available only to the respondent State. Thus, such evidence is actually lacking, as it is in the case. For this reason, even in this cases which mention the "use" by a respondent of the property at issue, the evidence has generally indicated- as in this case- only that the property had come into the respondent's hands and had been used to some extent by it. Having ascertained this fact, tribunals have not itemized and valued such "uses", but have awarded injured parties the value of the transferred property. Ibid. at pp. 213-14. In Mr. Holtzmann's view, the figure of USD 750000, which he stated the majority had pulled out of the air, was "derisory". Id. at p. 213.
101Flexi-Van Leasing, Inc., supra note 74, 12 Iran-U.S. Cl. Trib. Rep. 354. See also Dissenting Opinion of Howard M. Holtzmann in Flexi-Van Leasing, Inc., 12 Iran U.S. Cl. Trib. Rep. 356, 363 (stating, citing authority, that other international tribunals, rather than requiring proof of "actual use", have held that a benefit constituting unjust enrichment occurs when goods are available for use by a state, regardless of whether the claimant can show particular instances of that use).
102CENTRAL-List Rule, reprinted in Berger, Creeping Codification, supra note 2, at p. 295, and Berger, "Introduction", supra note 4, at p. 149.
103CENTRAL-List Rule, reprinted in Berger, Creeping Codification, supra note 2 at p. 295, and Berger, 'Introduction', supra note 4, at p. 148.
104Pomeroy Corp. v. Islamic Republic of Iran, Award No. 51-41-3, 2 Iran-U.S. Cl. Trib. Rep. 391, 397 (8 June 1983). See also RayGo Wagner Equipment Co. v. Star Line Iran Co., Award No. 20-17-3, Iran-U.S. Cl. Trib. Rep. 411, 413-14 (15 December 1982); Kimberly-Clark Corp. v. Bank Markazi Iran, Award No. 46-57-2, 2 Iran-U.S. Cl. Trib. Rep. 334, 339 (25 May 1983); R.N. Pomeroy v. Islamic Republic of Iran, Award No. 50-40-3, 2 Iran-U.S. Cl. Trib. Rep. 372-380 (8 June 1983); Chas. T. Main International, Inc. v. Khuzestan Water and Power Authority, Award No. ITL. 23-120-2, 3 Iran-U.S. Cl. Trib. Rep. 156, 163-64 (27 July 1983).
105Stephen G. Shifflette, supra note 29, 22 Iran-U.S. Cl. Trib. Rep. 115 para 18. See also DIC of Delaware, Inc., supra note 74, 8 Iran-U.S. Cl. Trib. Rep. 161 and Combustion Engineering, Inc., supra note 29, 26 Iran-U.S. Cl. Trib. Rep. 106 paras 161-63 (both holding that it is general principle of law that one can prove the existence of an enforceable contract through evidence demonstating part performance) and Woodward - Clyde Consultants v. Islamic Republic Iran, Award No. 73-67-3, 3 Iran-U.S. Cl. Trib. Rep. 239, 247 (2 September 1983) (holding that where the respondent orally consented to the claimant's services and paid for some of them, the respondent could not now avoid liability merely because neither party observed contract formalities').
106Intrend International, Inc. v. Imperial Iranian Air Force, Award No. 59-220-2, 3 Iran-U.S. Cl. Trib. Rep. 110, 115 (27 July 1983).
107General Dynamics Corp. v. Islamic Republic of Iran, Award No. 123-283-3, 5 Iran-U.S. Cl. Trib. Rep. 386, 394-95 (16 April 1984). Other cases in which the Tribunal has relied on the contemporaneous conduct of the parties in deciding questions of formation, validity, and interpretation of contracts include: Computer Sciences Corp., supra note 29, 10 Iran-U.S. Cl. Trib. Rep. 283; Reading and Bates Drilling Co. v. Islamic Republic of Iran, Award No. 355-10633-2, 18 Iran-U.S. Cl. Trib. Rep. 164, 172 para. 20 (16 March 1988); Seismograph Service Corp. v. National Iranian Oil Co., Award No. 420-443-3, 22 Iran-U.S. Cl. Trib. Rep. 3, 16 paras 41-42 (31 March 1989).
108Rexnord Inc. v. Islamic Republic of Iran, Award No. 21-132-3, 2 Iran-U.S. Cl. Trib. Rep. 6, 12 (10 January 1983). See also Westinghouse Electric Corp., supra note 29, 33 Iran-U.S. Cl. Trib. Rep. 154 para. 317 (rejecting for want of proof a claim that the claimant had charged exorbitant prices for spare parts on the ground that the respondent, as late as 1979, long after it had complained to the claimant about the prices, paid a number of the claimant's spares invoices).
109See John Carl Warnecke and Associates v. Bank Mellat, Award No. 72-124-3, 3 Iran-U.S. Cl. Trib. Rep 256, 261 (2 September 1983). Other cases in which the Tribunal has given significant weight to a party's failure to raise contemporaneous complaints include: Gould Marketing, Inc. (Final Award), supra note 45, 6 Iran-U.S. Cl. Trib. Rep. 277; Harnischfeger Corp. v. Ministry of Roads and Transportation, Award No. 144-180-3, 7 Iran-U.S. Cl. Trib. Rep. 90, 103 (13 July 1984);Blount Brothers Corp., supra note 47, 10 Iran-U.S. Cl. Trib. Rep. 67; The Trustees of Columbia University in the City of New York v. Islamic Republic of Iran, Award No. 222-10517-1, 10 Iran-U.S. Cl. Trib. Rep. 319, 326 para. 30 (16 April 1986); Logos Development Corp. v. Information Systems Iran of the Islamic Republic of Iran, Award No. 228-487-3, 11 Iran-U.S. Cl. Trib. Rep. 53, 65 para. 50 (30 April 1986), Mc Laughlin Enterprises, Ltd. v. Islamic Republic of Iran, Award No. 253-289-1, 12 Iran-U.S. Cl. Trib. Rep. 146, 150-51 para. 16 (16 September 1986); Ford Aerospace and Communications Corp., supra note 29, 14 Iran-U.S. Cl. Trib. Rep. 36, para. 47; Seismograph Service Corp., supra note 107, 22 Iran-U.S. Cl. Trib. Rep. 53-54 para. 193, 83 para. 320; Anaconda Iran, Inc. v. Islamic Republic of Iran, Final Award No. 539-167-3, 29 Iran-U.S. Cl. Trib. Rep. 320, 341-42 paras. 64-65, 367 para. 119 (29 October 1992); Westinghouse Electrc Corp., supra note 29, 33 Iran-U.S. Cl. Trib. Rep. 89 para 91. See also infra notes 117 and 118.
110Collins Systems International ,Inc., supra note 29, 28 Iran-U.S. Cl. Trib. Rep. 31 para. 29. See also ibid. at p. 32 para 34 (While the Tribunal has not considered itself bound by the parties' view as to whether a contract terminated, ... it has generally taken into account contemporaneous behavior in deciding that question'). Accord Westinghouse Electric Corp., supra note 29, 33 Iran U-S. Cl. Trib. Rep. 78 para. 53. See also Itel International Corp. v. Social Security Organization of Iran, Award No. 479-476-2, 24 Iran-U.S. Cl. Trib. Rep. 272, 283 para. 38 (23 May 1990); General Electric Co., supra note 29, 26 Iran-U.S. Cl. Trib. Rep. 158-61 paras. 32-40.
111Westinghouse Electric Corp., supra note 29, 33 Iran-U.S. Cl. Trib. Rep. 137. See also ibid. at p. 169 para. 360, 175 para. 379. The Tribunal applied similar reasoning in General Dynamics Telephone Systems Center, Inc., supra note 29, 9 Iran-U.S. Cl. Trib Rep. 159-60. See also Kimberly-Clark Corp., supra note 104, 2 Iran-U.S. Cl. Trib. Rep. 341-42.
112See Oil Field of Texas, Inc. v. Islamic Republic of Iran, Award No. 258-43-1, 12 Iran U.S. Cl. Trib. Rep. 308317 para. 35 (8 October 1986).
113Combustion Engineering, Inc., supra note 29, 26 Iran-U.S. Cl. Trib. Rep. 125-26 para. 240.
114Collins Systems International, Inc. supra note 29, 28 Iran-U.S. Cl. Trib. Rep. 39 para. 59. Cases in which the Tribunal has held that a party had waived a contractual right include: Lischem Corp. v. Atomic Energy Organization of Iran, Award No. 140-194-2, 7 Iran-U.S. Cl. Trib. Rep. 18, 23 (29 June 1984); Blount Brothers Corp., supra note 47, 10 Iran-U.S. Cl. Trib. Rep. 68; Logos Development Corp., supra note 109, 11 Iran-U.S. Cl. Trib. Rep. 64 para. 43; Howard Needles Tammen and Bergendoff v. Islamic Republic of Iran, Award No. 244-68-2, 11 Iran-U.S. Cl. Trib. Rep. 302, 330-31 paras. 105-107 (8 August 1986); Onesco, Inc. v. National Iranian Gas Co., Award No. 254-263-2, 12 Iran-U.S. Cl. Trib. Rep. 160, 167 para. 21 (18 September 1986); Cosmos Engineering, Inc. v. Ministry of Roads and Transportation, Award No. 271-334-2, 13 Iran-U.S. Cl. Trib. Rep. 179, 184-85 paras. 20-21 (24 November 1986); Whittaker Corp. v. Islamic Republic of Iran, award No. 301-286-1, 14 Iran-U.S. Cl. Trib. Rep. 263, 269-70 paras. 25-26 (27 April 1987). See also Phillips Petroleum Co. Iran v. Islamic Republic of Iran, Award No. 425-39-2, 21 Iran-U.S. Cl. Trib. Rep. 79, 155-56 paras. 198-99 (29 June 1989). Cases in which Tribunal has found that a party had not waived its contractual rights include General Dynamics Telephone Systems Center, Inc., supra note 29, 9 Iran-U.S. Cl. Trib. Rep. 162-63 and Unidyne Corp., supra note 29, 29 Iran-U.S. Cl. Trib. Rep. 326 para. 48.
115See, e.g. R.J. Reynolds Tobacco Co. v. Islamic Republic of Iran, Award No. 145-35-5, 7 Iran-U.S. Cl. Trib. Rep. 181, 190-91 (6 August 1984); DIC of Delaware, Inc., supra note 74, 8 Iran-U.S. Cl. Trib. Rep. 164; Sylvania Technical Systems, Inc., supra note 29, 8 Iran-U.S. Cl. Trib. Rep. 316; Questech, Inc., supra note 29, 9 Iran-U.S. Cl. Trib. Rep. 126; Touche Ross and Co., supra note 29, 9 Iran-U.S. Cl. Trib. Rep 298; Ford Aerospace and Communications Corp., supra note 29, 14 Iran-U.S. Cl. Trib. Rep. 41 para. 62; Harris International Telecommunications, Inc., supra note 29, 17 Iran-U.S. Cl. Trib. Rep. 73 para. 143; Houston Contracting Co., supra note 29, 20 Iran-U.S. Cl. Trib. Rep. 24-25 para. 73; Rockwell International Systems, Inc., supra note 29, 23 Iran-U.S. Cl. Trib. Rep. 183 para. 127, 188 para. 188; Collins Systems International, Inc., supra note 29, 28 Iran-U.S. 38-39 para. 57; Westinghouse Electric Corp., supra note 29, 33 Iran-U.S. Cl. Trib. Rep. 113 para. 164, 180-81 paras. 394-95; Gulf Associates, Inc. v. Islamic Republic of Iran, Award No. 594-385-2, para. 127 (7 October 1999) (not yet published in the Iran-U.S. Claims Tribunal Reports).
116See Westinghouse Electric corp., supra note 29, 33 Iran-U.S. Cl. Trib. Rep. 180-81 paras. 394-95.
117See, e.g., Richard D. Harza, supra note 29, 11 Iran-U.S. Cl. Trib. Rep. 114 para. 99; The Austin Co. v. Machine Sazi Arak, Award No. 257-295-2, 12 Iran-U.S Cl. Trib. Rep. 288, 294-95 paras. 31-32 (30 September 1986); Westinghouse Electric Corp., supra note 29, 33 Iran-U.S. Cl. Trib. Rep. 105-6 para. 141; 139-40 para 271.
118DIC of Delaware, Inc., supra note 74, 8 Iran-U.S. Cl. Trib. Rep. 176.
119It would extend beyond the scope of this article to explore whether the Tribunal, in its jurisprudence, has also developed any rules that now or in the future may be included in the body of the lex mercatoria. Berger describes this sort of evolution process as the 'development of individual rules from mere candidates to genuine components of die lex mercatoria.' Berger, Introduction, supra note 4, at p. 140 (footnote omitted). See also ibid. at pp. 140-44. On a related note, Crook writes that '[i]t would be useful to analyze the tribunal's contract cases in greater detail, to further examine key principles to be refined and appliecl in the future.' Crook, 'Debt and Contract Claims', supra note 22, at p. 300.
120Brower and Brueschke., supra note 15, at p. 669.
121Claims Settlement Declaration, supra note 12, article V. See text accompanying note 20.