33.3 Both the CONTRACTOR and the COMPANY agree that they will not, directly or indirectly, receive from, or give or offer to give to any member of the COMPANY GROUP or CONTRACTOR GROUP, or to other contractors or suppliers, or to government officials or any other persons anything of material value which would be regarded as an improper inducement to any party. Any breach of this obligation shall constitute a material breach of the CONTRACT.
[...]
Both the COMPANY and the CONTRACTOR shall take all reasonable steps to mitigate any losses resulting from any breach of CONTRACT by the other party.
35.1 If the CONTRACTOR fails to complete any of the items listed in Appendix 1 to Section I - Form of Agreement in accordance with the relevant date included in the SCHEDULE OF KEY DATES and/or fails to achieve the requirements of the CONTRACT in respect of any other items listed under the heading Clause 35.1 - Liquidated Damages in the said Appendix 1, the CONTRACTOR shall be liable to the COMPANY for Liquidated Damages. The amounts of such Liquidated Damages shall be as specified in the said Appendix 1.
35.2 All amounts of such Liquidated Damages for which the CONTRACTOR may become liable are agreed as a genuine pre-estimate of the losses which may be sustained by the COMPANY in the event that the CONTRACTOR fails in its respective obligations under the CONTRACT and not a penalty. Such Liquidated Damages shall be the sole and exclusive financial remedy of the COMPANY in respect of such failure.
35.3 If the CONTRACTOR can show that it has suffered delay as a direct result of the number of "waiting on weather days" exceeding the number of such days specified in Appendix 1 to Section I - Form of Agreement, then, subject to Clause 14, the COMPANY shall issue a VARIATION to adjust the SCHEDULE OF KEY DATES to take into account any such delay. Except as otherwise provided in the CONTRACT, no adjustments to the CONTRACT PRICE shall be made in respect of any such delay.
[...]